BORED PILING WORKS

CSI had sought the expertise of Redviper on bored piling works for the construction of 800 meter diameter by 13 meter with a total number of 32 concrete piles for the 800,000 MTPA Bar Rolling Mill Project has successfully accomplished on time. RVDC proficiency in infrastructure development has proved again its capability of engineering foundation.